Longwall complex efficient time and reasons of its decreasing
Abstract
Degree of calendar time use in fully mechanized Longwall system has fundamental affect
for this system capacity and its efficiency. Extraction process realized by fully mechanized longwall
system time when cutting machine (shearer or plow) is not cutting is, in economical point of view,
is not effective, wasted time. In coal extraction process realized by fully mechanized longwall
complex are breaks in cutting as result of many different reasons. Some of those break have source
in necessary in used mining technology and technical system constrains. In article is presented
longwall face calendar time structure and analyzed sources of efficient time loses. Only cutting time
as a part of calendar time is efficient. Three mine, different group of efficient time loses as mining
technology, extraction process management or longwall equipment quality (reliability) and
maintenance needs are definied.
Copyright (c) 2022 Jacek Korski
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
This journal permits and encourages authors to post items submitted to the journal on personal websites or institutional repositories both prior to and after publication, while providing bibliographic details that credit, if applicable, its publication in this journal.